10.15.2010
10.04.2010
8.20.2010
The finishing touches
Aiming to get this project done by sept 1st. Realizing how little documentation there has been on the phase II progress. Instead I'll just end with some great before and after photos. Here are a few mid-project
7.16.2010
Sheetrocking
The status of apartment 1 is: a mess.
But we are on schedule with completing the work by September.
Now it's up to us to figure out finish floor material. Were planning on bamboo @1.89/sq ft, and in the kitchen outdoor deck paint on plywood floor. Kind of like our bedrooms on the top floor, but possibly oil based for a more substantial coat.
But we are on schedule with completing the work by September.
Now it's up to us to figure out finish floor material. Were planning on bamboo @1.89/sq ft, and in the kitchen outdoor deck paint on plywood floor. Kind of like our bedrooms on the top floor, but possibly oil based for a more substantial coat.
6.25.2010
Intermission...
It's been months since I've updated, lots of little finishing touches on our apartment. Soon I will upload some videos of phase II, a much more extensive renovation.
In the meantime, here are a few pics of our outdoor spaces.
In the meantime, here are a few pics of our outdoor spaces.
6.03.2010
Stairway
Two months since my last post! Well, to conclude 3 Highland Phase I, we did some exterior work, which involved building this staircase. We were seeking a safe way to get to the roof that wasnt a rickety ladder. Ama and I build this alternating tread staircase that's shape was calculated based on ama's stair stride. Now we are figuring out a way to incorporate a railing. Updates and better pictures will follow!